Repetitive Work cycle

A time study analyst observed a repetitive work cycle performed by a worker and then studied the task using a predetermined motion time system. During the observation, the analyst made a record of the work elements. She also made a note of the worker’s performance and rated as 105%. Back in the office, the analyst listed the basic motion elements for the task and calculated the sum of the normal times equals 1.38 minutes. The company uses a PFD allowance factor of 15%. Determine the standard time for the task to three decimal places. Show all work for full credit.